Copy an Object to Another Floor

A building's foundation, walls of different floors, floors, ceilings, roof, etc. are added in their own drawing-model pairs. If necessary, you can copy objects from the active drawing-model pair to another drawing-model pair of the same project. If, for example, the exterior walls of a building are similar on both the first and second floors of the building, you can copy the walls of the first floor to the floor plan of the second floor.

Connections to other building components are also copied, if the connecting structures are equivalent in the floors.

  1. Activate the drawing-model pair in which the objects to be copied are.
  2. Select one or more objects.
  3. Right-click to open the context-sensitive menu.
  4. Select Advanced > Copy to Another Floor.
  5. Select the drawing-model pair to which you want to copy the objects. Click the button of the drawing-model pair in a button menu. You will be prompted: "Leave this drawing-model pair active?" The question refers to the drawing-model pair to which you are copying the objects.
  6. Do either of the following:
Note

Select an Object
Copy an Object within a Drawing/Model
Copy Objects to Another Project
Copy an Object to the Clipboard
Drawing-Model Pairs of a Project

Converted from CHM to HTML with chm2web Pro 2.85 (unicode)