Framer, Floor Framing & Rafters

Insulation

You can use this function to add a continuous insulation layer on a limited area in the horizontal structure.

  1. Select Floor Joists, Roof Rafters > Insulation > Add Insulation.
  2. Select the method of selecting structural layer from the contextual toolbar.

    Selecting Structural Layers

  3. Select the area.
  4. Select the insulation properties in the Wool Data dialog box.

    Wool Data dialog box

  5. Select the corner points of the area to which insulation is to be added.
  6. Select Confirm.

The insulation layer is added to the framing model FRAMING.vxm.

Adding Insulation Into Area
Adding Insulation Into Limited Area
Deleting Insulation

Converted from CHM to HTML with chm2web Pro 2.85 (unicode)