Project Revisions
You can create a master revision database for adding information
of all the changes made to the project. You can copy the change
information into the revision data of any document in the project.
You can add the revision data as a text macro in a drawing.
- Open the project for which you want to add revision
information.
- Activate any of the project's drawing-model pairs or drawing
sheets.
- Do one of the following:
- Right-click in the active document to open the
context-sensitive menu and select Active Document Data from
the menu.
- Select File > Document Archive > Edit Active
Document from the menu bar.
- Select File > Document Archive > Edit All Project
Documents from the menu bar.
The Project Document Information database view
is opened.
- Activate the Document Revisions database view under the Project
Document Information database view.
- Click the Master button. The Project Revisions database
view opens.
- Add a row to the database by clicking the Add row
button.
- Fill in the change data in the text fields.
- No - Type the revision number in the text field.
- Date - Add today's date by clicking the Date
button. You can also type the desired date to the field in the
format dd.mm.yyyy, for example 15.11.2004.
- Designer
- Remark - Type a description of the revision in the text
field.
- Time used
- Billing information
- Confirm by clicking OK. You will return to the Document
Revisions database view.
- You can copy the project's revision information into the
revision data of the active document by clicking the Select
button. Select the desired row in the Project Revisions database
view, and accept by clicking OK.
Note
- The project revisions are saved in the REVMASTER database in
the project's folder.
Document
Revisions