Option System |
The schedules of floor joists and other profiles will be refreshed during option testing/solving, when the following definition has been set up for the schedule in question in the BDSXX keyword group:
In addition, updating of piece schedules is controlled with the keyword upd_piece_schedules_during_testing in the BDSXX keyword group. The keyword can have the following values:
Default value (also when the keyword has not been set). Piece schedules that have the OPT.UPDATE ON definition will be updated during option testing/solving.
The program prompts the user whether to update the piece schedules that have the OPT.UPDATE ON definition.
The piece schedules will not be updated and no confirmation will be asked from the user.
Testing
Options
Solving Options
Editing
Keywords